A major infrastructure rerouting operation required the evacuation of a 60-mile section of 26-inch pipeline. The client sought a solution that ensured quick turnaround, minimized emissions, and maintained full gas recovery without flaring.
Starting from 698 PSIG, ReCo deployed a high-capacity mobile compression setup that safely reduced the pipeline pressure to 48 PSIG over the span of four days.
More than 54 MMSCF of natural gas was recovered and redirected for reuse. The project was completed within the expected timeframe, highlighting ReCo’s ability to manage high-volume, long-distance recompression tasks with precision and environmental accountability.